SUNY Plattsburgh Campus Project 2004/2005

(Word - 35k, PDF - 22k)

MAJOR FUND PROJECTS DESCRIPTION REMARKS/STATUS
Soccer/Lacrosse Field On schedule. Installation of lighting to begin by June 15, with an expected completion date of July 15. Installation of turf to begin by July 1 and be completed by August 1. Project to be completed by August 15, 2004.  
Sibley Hall Phase I Beneficial occupancy June 4; punch list to follow. Official occupancy by August 1, 2004.  

CAMPUS LET PROJECTS DESCRIPTION REMARKS/STATUS
Outdoor Track/ Practice Field @ Fieldhouse

Asphalt surface to be applied July 1. Rubberized coating applied August 1. Expected project completion date August 15, 2004 Practice Field proceeding as Campus LET (180,00)

To upgrade athletic track and fields, rough grade to be completed by June 14, final grade with top soil by June 21 and final seed by June 28. Hopefully (mother nature permitting) will have grass by September 1. Touch and go as far as usability for the fall.

 
Hudson 106 / Smart Classrooms Consultant on Board. Demolition to begin July 1 consultant to follow. Expected completion date January 1, 2005. 4 Smart classrooms to follow. Separated from Main Hudson 106 Project to avoid any potential hang-ups in proceeding with the Campus LET. Will be added to that project when Consultant is brought on board. Hopefully can get 2 done (possibly late summer) with the other 2 during the semester break.  
Algonquin Roof In design stage; to be bid by July 1 with installation October 2004.  
Hawkins/Kehoe Site Work To begin by July 1, with completion by Aug. 20, 2004.  
Hawkins Pond Internal study in progress.  
CHP Generator Bid has been awarded; installation to be completed by mid October 2004.  
Library HVAC In the process of reviewing consultant proposals. Bit of a glich in that NYS power authority has indicated that they might be interested in the project but I can see some funding problems so we are still proceeding as if it will be a Campus LET. Decision should be made by August 1st allowing us time for design and installation by early spring. We were hoping that the FUND would have their regional consultant program in place as promised so we could avoid the several month process of evaluation consultant proposals but that has yet to be established.  
New Storage Proposed Campus LET. Met with consultant on June 8. Concept meeting on June 15. Plot plan, layout by June 15. Bid documents August 15. Award by September 15. Construction complete by November 1, 2004.  

RESIDENCE HALLS DESCRIPTION REMARKS/STATUS
MacDonough Phase I HTHW line installed by August 15. Open sidewalk from Angell College Center to Myers Fine Arts July 1 Aug. 1 Dorm occupancy by August 15, 2004.
 
Fire Alarm Will Complete Hood, deFredenburgh, Moffitt.. Wilson and Harrington next year will complete Residence Hall projects. MacDonough included in current major rehab.  
Harrington Hall Install fire doors and add two additional door units;
Expected completion date July 15, 2004
 

M & R DESCRIPTION REMARKS/STATUS
Myers Fine Arts Outside exit added to Room 129 to be completed by July 15, 2004. Room 108 total rehabilitation of Sculpture lab.  
Outdoor Lighting Angell Ctr./ CV Hall / Banks Hall Replace 24 lights and poles; to be completed by August 15, 2004.  
Sibley Hall Add ADA ramps and replace two doors; to be completed by August 1, 2004.  

MISC. DESCRIPTION REMARKS/STATUS
Flower Beds Add to 102 Broad between Rugar Street and Myers Fine Arts and between Rugar Street and Angell College Center.  

Contact Information

For more information about the Capital Planning Committee at SUNY Plattsburgh, please contact:

Carol Bleaux, Chairperson
Office: Feinberg 116J
Phone: (518) 564-2434
E-mail: carol.bleaux@plattsburgh.edu