Plattsburgh Project Number Project Description Design Phase Begin Construction Phase Occupancy Date Current Phase
Note: these projects will start & finish in the current capital plan (2004-2008)
11246 Replace Primary Electrical Distribution Sys 2005 2006 2007 Under Construction
11254 Replace HTHW Generator - CHP 2005 2007 2007 Contract Awarded
11260 Construct Campus Storage Facility 2006 2006 2007 Under Construction
11253 Replace HTHW - Phase II 2006 2007 2007 Design
11268 Soil Remediation UST Service Building 2006 2007 2007 Design
11264 Emerg Rep to Condensate Lines Kehoe 2006 2007 2007 Contract Awarded
11292 Chiller and Tower Replacement Feinberg 2006 2007 2007 Contract Awarded
11269 Campus Substation Transformer 2007 2007 2007 Contract Awarded
TBD ADA Compl. Install Elevators (Saranac) 2007 2007 2007 Design

Projects Start & Finish in Current Cap Plan (2004-2008)

Plattsburgh Project Number Project Description Design Phase Begin Construction Phase Occupancy Date Current Phase
11215 Exterior Renovation to Fieldhouse 2003 2004 2006 Completed
11263 Replace Garage Lift, Service Building 2005 2006 2006 Completed
11267 Elevator Rehab DASNY JOC's Construction 2005 2006 2007 Completed
11259 Demolish Maintenance Storage Building 2006 2007 2008 Design
11252 Hudson Hall Phase I 2006 2008 2010 Design
11217 ADA Compl. Install Elevators - SAR, FH, MEM (Design Only) 2007     Design
11261 Champlain Valley Hall Window Replacement 2007 2008 2008 Identified
11296 Winkle Court Rehab/Repair 2007 2008 2008 Design
11244 Replace Ice Rink Seating Phase I 2007 2008 2008 Design

Projects That Start in the Current and Finish in Next Capital Plan
(Current = 2004-2008, Next = 2009-2013)

Plattsburgh Project Number Project Description Design Phase Begin Construction Phase Occupancy Date Current Phase
11228 Replace Cooling Towers/Chillers - Var. Bldgs. 2007 2009 2010 Design
11226 ADA Compl. Install Elevators (FH, MEM)   2009 2010 Design
11223 Exterior Masonary Repair and Replace 2008 2009 2009 Identified
11230 Exterior Site Safety Master Plan 2008 2010 2013 Identified
11243 Rehab Field House Mechanical Systems 2008 2009 2010 Identified
11262 Champlain Valley Hall Roof Replacement 2009 2010 2010 Identified

Projects That Start & Finish in the Next Capital Plan (2009 - 2013)

Plattsburgh Project Number Project Description Design Phase Begin Construction Phase Occupancy Date Current Phase
TBD Beaumont Mechanicals 2009 2010 2010 Identified
11222 Repair/Replace Roofs (Angel, Feinberg, Sibley) 2009 2010 2011 Identified
11238 Window Replacement (MEM SAR RED SIB) 2009 2010 2013 Identified
11240 Upgrade Sibley Hall Mechanical Systems 2010 2011 2012 Identified
11233 Upgrade Emerg Exit Signage Campuswide 2010 2012 2014 Identified

Projects That Start & Finish in Subsequent Capital Plans (2014-2018)

Plattsburgh Project Number Project Description Design Phase Begin Construction Phase Occupancy Date Current Phase
TBD Install Lockerrooms Field House Phase II 2012 2013 2014 Identified
11229 Gut/Rehab Ward Hall 2013 2014 2015 Identified
11241 Rehab Kehoe Exterior 2013 2014 2015 Identified
11239 Rehab Sibley Exterior 2014 2015 2016 Identified
11231 Renovate Pool for Code Compliance - Bldg. 11 2014 2016 2018 Identified
11224 Rehab Beaumont 2015 2017 2019 Identified

Contact Information

For more information about the Capital Planning Committee at SUNY Plattsburgh, please contact:

Carol Bleaux, Chairperson
Office: Feinberg 116J
Phone: (518) 564-2434
E-mail: carol.bleaux@plattsburgh.edu